Sidewalk and curb replacement construction is scheduled to begin on May 22, 2023 along both Park Avenue and 23rd Street around the City Park. This project is expected to be completed by mid-June of this year. This project consists of approximately 1500ft of new curb along the Park Avenue side of the park as well as about 1400ft of new sidewalk and curbs along the 23rd Street side of the park. The Contractor plans to start on the Park Avenue side and then begin to work toward 23rd Street. The City is asking residents traveling in these areas to be cautious of new traffic patterns as the construction progresses. We appreciate your patience and understanding!
- The contractor is Alan Stone Company Inc
- Total project cost $295,500